To improve the working environment mixing station site

Ready mix concrete plant be set at least two cement silos, a fly ash silo, a slag silos. In order to prevent the powder inside the silo arch plugs, silo should have broken arch; mixing station site in order to improve the working environment, to cement silo breeze requirements dust, top of the silo should be automatic cleaning equipment; In order to detect cement cement silo storage capacity silo material level indicator should be set; powder for monitoring the temperature inside the silo, silos should be set within a temperature sensor; For ease of testing samples from the silo should set up a dedicated sampling port; in order to ensure safety, ready mix concrete plant devices must be located at the top of the silo. To ensure safety, must be the foundation bearing capacity silos and mixers for field tests, such as bearing capacity can not meet the silos and mixers foundation bearing capacity requirements, you need to fill the foundation for change process.